Amid a surge in demand for photo voltaic backup methods pushed by elevated load-shedding, Cape City is clamping down on defective installations by banning off-grid inverters for grid-connected properties. Beginning October 1, 2023, town will mandate using permitted inverters for photo voltaic and battery methods, streamlining the authorisation course of and enhancing security. The transfer goals to forestall space outages and make sure the integrity of the community. Whereas some residents increase considerations about the associated fee, town’s measures additionally allow owners to earn for surplus electrical energy and cut back AMI meter prices.
Join your early morning brew of the BizNews Insider to maintain you in control with the content material that issues. The publication will land in your inbox at 5:30am weekdays. Register right here.
Why Cape City is banning off-grid inverters for photo voltaic installations
By Hanno Labuschagne
The Metropolis of Cape City will cease approving off-grid inverters to be used in photo voltaic backup methods to curb defective and harmful installations of those inverters in households that stay related to the grid.
As a result of improve in load-shedding, town has seen an enormous surge in purposes for grid-tied photo voltaic and backup methods, with a mean of over 1,000 per 30 days in 2023 in comparison with 100-200 a yr in the past.
From 1 October 2023, Cape City would require that new purposes for photo voltaic PV and battery methods related to a constructing’s wiring use a city-approved inverter and procure skilled clearance.
It is going to additionally refuse purposes for standby and off-grid methods.
Learn extra: South Africa’s wind energy surge: 34 wind farms generate over 3,400MW (with extra on the horizon!)
The town defined that contemplating all methods as grid-tied would dramatically enhance authorisation turnaround time, enhance security, and forestall the chance of space outages resulting from inferior methods related to the grid by fly-by-night operators.
“At present, many methods utilizing non-approved inverters are usually not wired accurately, posing dangers to the protection and integrity of the community,” town stated.
“This considerably slows down the registration course of as a result of there are too many various wiring configurations for town professionals to think about. Decreasing the wiring configurations quickens the method.”
The brand new guidelines is not going to apply to cellular options like trolley inverters or energy stations that may be plugged into wall sockets.
It is going to additionally not apply to eventualities the place residents utterly sever their properties from the grid.
The town’s laws apply solely the place there’s a connection to the electrical energy community.
A number of upset residents contacted MyBroadband concerning the subject, stating that the hybrid inverters on town’s permitted checklist had been considerably dearer than off-grid fashions.
Common off-grid models usually come white-labelled from manufacturers like Axpert, Growatt, Kodak, and Mecer, and may begin at lower than R10,000 with a capability of 5kW.
Hybrid inverters with the identical capability are usually priced between R20,000 to R30,000.
Probably the most inexpensive hybrid inverter listed on Photo voltaic Recommendation’s web site is the LuxPowerTek 5kW unit, which prices R20,125.
The identical producer’s off-grid inverter prices R11,902.50 from the identical retailer.
An off-grid inverter may also be related to the grid however just isn’t designed for this function.
Whereas a hybrid inverter can use a mixture of photo voltaic and grid electrical energy, an off-grid inverter can solely use one supply at a time.
In case your photo voltaic capability turns into inadequate, an off-grid inverter will routinely change to grid-only energy.
Nonetheless, throughout a small-scale power generator (SSEG) installer occasion held by town, it turned clear that some installers had been connecting cheaper off-grid inverters incorrectly.
The town advised attendees it had obtained 120 purposes from only one installer who claimed their setups had been off-grid however had been discovered to be grid-tied upon inspection.
“Sensible expertise exhibits us that standby SSEG methods are sometimes not configured accurately,” town stated.
“Standby inverters are usually not NRS 097-2-1 permitted and have to be remoted from the grid through an interlocked changeover change.”
It additionally found situations the place “off-grid” methods had their meters operating backwards, that means consumed electrical energy was mirrored as being fed into the grid.
That might end in households and companies getting paid for electrical energy they’d consumed.
The town stated the responsible installers had refused to adjust to its laws, claiming that the methods had been just for standby.
There had been little to no repercussions from the Division of Labour for poor electrical installations both, whereas fireplace harm resulting from poor workmanship and non-compliant elements had elevated six-fold in a couple of years.
AWPower managing director Christiaan Hattingh advised MyBroadband that the principles about photo voltaic installations in Cape City had at all times been clear.
“For those who needed to go the photo voltaic route, your inverter wanted to be on the Metropolis of Cape City’s Accredited Inverters Listing,” Hattingh stated.
He defined these inverters had been examined in accordance with the NRS 097-2-1 customary.
Relating to SSEG, the specification units out the technical necessities for the utility interface, the embedded generator and system, and the utility distribution community with respect to embedded era.
Learn extra: Powering change: Load-shedding disaster unlocks power funding alternatives
Influence on grid-tied properties planning to get photo voltaic
Hattingh stated when the brand new guidelines come into impact, households with off-grid inverters received’t be allowed to put in photo voltaic if they’re related to the grid.
Along with the requirement that every one inverters be on town’s permitted checklist and no off-grid inverters can be allowed, town can be constructing an internet SSEG software system.
Except for the protection and approval advantages, utilizing a hybrid inverter will permit clients to receives a commission for electrical energy they feed again into the grid at R1.13 per kWh till June 2025.
Lastly, town can be conscious that the price of Superior Metering Infrastructure (AMI) meters was a significant barrier for residential clients wanting to put in grid-tied methods.
It has issued a brand new tender that features the supply of single-phase AMIs at a “considerably” lowered value, though the pricing for this stays to be confirmed.
The Residential AMI Entry Charge of R96.20 per 30 days can be being changed by a brand new residential AMI Administration Charge of R5.66.
Learn additionally:
This text was first printed by MyBroadBand and is republished with permission